Is the shed empty?
If it is and it's on relatively level ground the whole distance of the move, a jack or pry bar to lift the shed onto the first pipe and then 3 or more lengths of 3" or 4" PVC pipe the width or more of the shed, plus 2-3 adult men should be all you need. One person moves the pipes back to front while others move the building, keeping it on at least 2 pipes the whole move. As the building rolls off each pipe, the pipe mover relocates the pipe to the front of the building and then the building is moved forward again, keeping it on at least two pipes the whole way.
I live in Kannapolis near Lake Concord, but I'm 81 and have too much wrong with me to be of much help, but I have moved small buildings like this several times in my life, even doing it alone. It's easy if conditions are right and you plan the path and equipment needed well.
Then there's the Amish way
Charley