I have finally outgrown my current mechanics, wood and general storage shop. I will retain this current shop (520 sqft) for mechanics and wood storage.
My new shop will be reserved for woodworking.
Here are the specs:
Size: 24 x 28 main room with 8 x 23 wing for 856 sqft
Foundation: full block/brick to match house
Floor system: 2x8 16"oc spanning less than 8' with 1" Advantec flooring
Walls: 9' or 10' 2x4 with osb 7/16 sheathing, brick veneer in front and Hardie on other 3 sides
Roof: Vaulted with 2x6 16"oc rafters, 3 1/2" x 18" x 24' lvl ridge beam and 5/8 osb sheathing
Windows: seven Pella double-hung and probably two Velux skylights
Entrance: double 3/0 x 7/0 steel door with ramp down to sidewalk
Interior walls: 5/8 fire-code drywall
Ceiling: Vaulted drywall up to 13' acoustical level center section allowing easy access above
Insulation: floor r19, walls r15, ceiling r33
Electrical: 200 amp subpanel fed from house main
Heating/cooling: spare 3 ton 12 seer Carrier heat pump
Lighting: T5 HO dimmable at 13' level, track lighting on vaulted sections
Compressed air: 60 gal 2 cyl Energair in attached shed with IR aluminum tubing distribution
Dust collection: Underfloor 6" ducts probably powered by Clearvue cyclone with temp sensing venting. One retractable overhead duct for tablesaw
Finishing room: 8 x 8 "clean room" in the 8 x 23 wing
Crawl space: double 3/0 x 6/0 doors, 20 mil poly floor, 50 cfm 24/7 vent fan
I have contracted the foundation work. I plan on doing the rest myself, I am hoping to host an equipment moving party in early November.
Here are some startup photos, I will post progress photos.
My new shop will be reserved for woodworking.
Here are the specs:
Size: 24 x 28 main room with 8 x 23 wing for 856 sqft
Foundation: full block/brick to match house
Floor system: 2x8 16"oc spanning less than 8' with 1" Advantec flooring
Walls: 9' or 10' 2x4 with osb 7/16 sheathing, brick veneer in front and Hardie on other 3 sides
Roof: Vaulted with 2x6 16"oc rafters, 3 1/2" x 18" x 24' lvl ridge beam and 5/8 osb sheathing
Windows: seven Pella double-hung and probably two Velux skylights
Entrance: double 3/0 x 7/0 steel door with ramp down to sidewalk
Interior walls: 5/8 fire-code drywall
Ceiling: Vaulted drywall up to 13' acoustical level center section allowing easy access above
Insulation: floor r19, walls r15, ceiling r33
Electrical: 200 amp subpanel fed from house main
Heating/cooling: spare 3 ton 12 seer Carrier heat pump
Lighting: T5 HO dimmable at 13' level, track lighting on vaulted sections
Compressed air: 60 gal 2 cyl Energair in attached shed with IR aluminum tubing distribution
Dust collection: Underfloor 6" ducts probably powered by Clearvue cyclone with temp sensing venting. One retractable overhead duct for tablesaw
Finishing room: 8 x 8 "clean room" in the 8 x 23 wing
Crawl space: double 3/0 x 6/0 doors, 20 mil poly floor, 50 cfm 24/7 vent fan
I have contracted the foundation work. I plan on doing the rest myself, I am hoping to host an equipment moving party in early November.
Here are some startup photos, I will post progress photos.